complete

Key Ceremony June 22, 2011.

                                                                   thumb_P1020137

TO LOCK UP:

  • Site Prep and excavation                                                       
  • Flat work, ICF Basement and floor 
  • Framing exterior and interior                                                                          
  • Doors and windows 
  • Roofing 
  • Mechanical rough-in 
  • Siding 

AFTER LOCK UP:

  • Soffit and facia 
  • Insulation and poly 
  • Drywall 
  • Paint  
  • Millwork
  • Interior doors and trim 
  • Finishing mechanical and skim coat 
  • Flooring 

LANDSCAPE:                                                                   

  • Fencing 
  • Sod 
  • Deck 
  • Key Ceremony